One measure.
Two geographies.
Compare the United States and China through consistent units, explicit boundaries and dated evidence. Geography reveals where demand meets the grid.
Latest Updates · 17 November 2026
Measured, approved and forecast · evidence register
NEWSource release dates range from 30 October to 16 November 2026. Keep policy coverage, approved projects, metered consumption and forecast power growth in separate statistical categories.
- 24 provinces · as of 2026-09-30 — Chinese provinces reporting implementing documents for green direct connections Original source ↗
- 12 approvals · as of 2026-09-30 — Approved green-power direct-connection projects involving computing facilities; approvals, not a count of commissioned projects Original source ↗
- 2.031 TWh / 56% · Ningxia, January–September 2026 — Reported compute-sector electricity use and green electricity share; the 2025 proportion uses a different period and must not be conflated Original source ↗
- +1.8 GW / +4.7 GW · CAISO plan estimates to 2030 / 2035 (January 2026 forecast quoted November) — Forecast data-center demand additions, not deployed new load Original source ↗
The scale of demandENERGY IN CONTEXT
Estimated global data center electricity use
Projected global data center electricity use
Combined share of global use: approximately 45% + 25%
Shares of global data center electricity use, 2024
Source: IEA, Energy and AI (2025). Figures cover all data centers, not AI alone, facility counts or installed capacity. The remaining 30% is calculated as 100% − 45% − 25%. The 2030 value is a projection.
2026 update (IEA, 14 October): 134 identified data-centre electricity-integration policies and regulations across more than 34 jurisdictions (about 90% of global data-centre capacity). Operators signed 45 TWh of PPAs in the first half of 2026 (almost 70% US). These are policy inventory and contracted-energy measures — NOT additional metered electricity use. IEA source ↗
2026 evidence register
- Green direct-connection policy coverage: 24 provinces · View latest source and boundary
- Approved computing-linked direct connections: 12 approvals · View latest source and boundary
- Ningxia measured electricity: 2.031 TWh / 56% · View latest source and boundary
- CAISO forecast additions: +1.8 GW / +4.7 GW · View latest source and boundary
A timeline of evidencePOLICY / CASE / EVIDENCE
Computing-hub implementation plan issued
A starting point for tracing national planning into local projects and power arrangements.
Read the policy commentary →Susquehanna interconnection amendment decision
The justification for non-standard terms provides a concrete entry into co-location research.
Read the order commentary →IEA publishes Energy and AI
The 2024 estimate and 2030 projection provide a common quantitative background.
Read the report ↗Large-load regulation meets long-term supply commitments
FERC accepted the PJM 50 MW Large Load Registry while rejecting the proposed IRAS/BYONC scheme. Google–Constellation, Amazon–Constellation and AEP–Google show distinct routes to contracted generation. The IEA report quantifies policy growth and signed PPAs; numbers are not plant output or metered demand.
FERC order → · Google nuclear PPA → · Cheyenne fuel cells → · IEA research →